Journal·Renovating in the UK: What Happens in What Order

November 10, 2026

Renovating in the UK: What Happens in What Order

The order of a UK renovation, from the brief to the completion certificate, and where planning, building regulations, party walls and design fit.

Renovating in the UK: What Happens in What Order

Most renovation delays are not caused by builders. They are caused by decisions made in the wrong order: a planning application drawn before the layout was settled, a kitchen chosen after the steels were in the wrong place, a party wall notice served the week work was due to start.

This guide sets out the order of a typical UK renovation or extension, from the first idea to the completion certificate, and where the design decisions belong along the way.

1. Brief and budget

Write down what you want the house to do that it does not do now: more light in the kitchen, a bedroom for a growing family, a study, a better route to the garden. Then set a budget, with a contingency for the unexpected. Older houses in particular hide surprises, and many people hold back around 10 to 15 percent.

Be honest about priorities. If the budget cannot do everything, the brief should say which things matter most.

2. Measured survey

Every good design starts from an accurate drawing of what exists. A measured survey records the walls, openings, levels and heights of the house, and often the garden and boundaries. It is the base for every drawing that follows, and errors here repeat through the whole project.

3. Layout and design, in 3D

This is the stage that decides how the house will feel, and the one most often rushed. Settle the layout before anything is submitted: where the kitchen goes, how big the openings are, where the glazing and rooflights sit, how the old house meets the new.

Seeing the design in 3D at this point costs far less than discovering it on site. A photorealistic render of the new kitchen-diner, or the loft, or the side return, shows the light, the proportions and the materials while everything can still change at the cost of a revision round. We do this for UK homeowners every week, in UK hours and with quotes in pounds; see our service for UK homeowners.

Open-plan kitchen and dining room in a new Munich home, with taupe cabinets, glass-fronted wall units, dark stone worktops and herringbone oak floor
Rainy Day in München, Munich, Germany

4. Planning permission or a lawful development certificate

If the work needs planning permission, the application goes in now, with drawings based on the settled design. Householder applications have a target decision time of eight weeks from validation. If the work falls under permitted development, a lawful development certificate confirms it in writing, which is useful when you sell. Our guides to planning drawings and permitted development explain both.

5. Building regulations drawings and building control

Once the planning position is clear, the design is developed into building regulations drawings: structure, with a structural engineer's calculations for steels and foundations, insulation, fire safety, drainage and ventilation. These go to a building control body, either the local authority or a registered building control approver, usually as a full plans application so the design is approved before work starts.

6. Party wall notices

If the work affects a wall you share with a neighbour, such as steels bearing on the party wall in a terrace, a loft conversion, or excavating for foundations close to a neighbour's, the Party Wall etc. Act 1996 requires you to serve notice. Depending on the work, notice is due one or two months before it starts. The neighbour can consent or dissent; if they dissent, surveyors agree an award setting out how the work will be done.

Serving notice early, often while planning is under way, keeps it off the critical path.

7. Tender and choose a builder

Send the same complete set of drawings, with a specification and finishes schedule, to each builder you invite to quote. Quotes priced from the same information can be compared like for like; quotes priced from a sketch cannot. Renders help here too: builders price more accurately when they can see the finished result you expect.

8. Order long-lead items

Bespoke kitchens, steel or aluminium glazing, rooflights, joinery and some tiles and stone can take weeks or months to arrive. Order them as soon as the design is fixed and the builder is appointed, so the build is not waiting for them.

This is also why the kitchen design belongs at stage 3, not here. Its layout decides where drainage, power and extraction go, and those are built in early.

9. The build

A typical sequence on site runs:

  • Strip-out and demolition, with protection for anything being kept
  • Structure: foundations, steels, new walls and roof
  • Weathertight: windows, doors and roof finished
  • First fix: cables, pipes and ducts run through open walls and floors
  • Plastering and screeding
  • Second fix: sockets, switches, sanitaryware, kitchen fitting and joinery
  • Finishes: flooring, decoration, lighting and final fixtures

Most changes cost least before first fix and most after plastering. Make sure your lighting plan is complete before first fix.

10. Sign-off

At the end, building control issues a completion certificate, and electrical and gas work comes with its own certificates. Keep them all with your planning documents: you will need them when you sell.

3D rendering of a living area with terracotta lounge chairs, stacked globe floor lamp and nesting stone coffee tables, Pasadena, California
Saffron & Stone, Pasadena, USA

The short version

Design first, then permissions, then builders, then the build. Most expensive mistakes come from doing one of those out of order. If you are starting out, our guides to loft conversions, Victorian terraces and garage conversions go deeper into the most common UK projects.

Frequently asked questions

What order should you renovate a house in?

Brief and budget, measured survey, design, planning permission or a lawful development certificate, building regulations drawings, party wall notices, tender, ordering long-lead items, the build itself (structure, first fix, plastering, second fix, finishes), and finally sign-off by building control.

When should I serve a party wall notice?

As early as you can once the design is settled, and at least one or two months before the relevant work starts, depending on its type. Many people serve notice while the planning application is being decided.

What is the difference between planning permission and building regulations?

Planning permission is about whether the development is acceptable in its location: its size, appearance and effect on neighbours. Building regulations are about how it is built: structure, fire safety, insulation, drainage and ventilation. Many projects need both.

When should I choose the kitchen in an extension?

During the design stage, before planning drawings are finalised. The kitchen layout decides where drainage, power, extraction and glazing go, and those are built in early.